Project Status (Updated Sep, 30, 2011)
Engineering, Procurement and Construction Update: Engineering for
the project has advanced to the final design. The Independent Electricity System Operator (IESO) of
Ontario has completed its system impact assessment of the project
and found that the project will improve the reliability and
integrity of the electrical system in the GTA and beyond. Hydro One
has completed its customer impact assessment of the project.
The Ontario Municipal Board (OMB) has completed a hearing of the project and
decided that the plant “will contribute to the supply of electrical power in
Mississauga and fulfill a need for electrical power generation within that
municipality” and, that “this, in the Board’s view, is a tangible public
benefit.” Greenfield South and the City of Mississauga are now implementing the
site plan and related approvals. The City of Mississauga’s Council approved the
project’s development agreement and related documents in December, 2008.
Greenfield South has completed the environmental assessment process and all
technical and regulatory requirements have been met as verified by the decision
of the Director of the Environmental Assessment and Approvals Branch (EAAB) of
the Ontario Ministry of the Environment (MOE) issued on January 19, 2006. The
Minister of the Environment confirmed the completion of the environmental
assessment process in July, 2008. The Ministry of the Environment issued the
Certificate of Approval (Air) in December, 2008.
All
financing needed for construction of the Project was finalized in May 2011.
Purchase orders for all major equipment for the facility including the turbines,
generators, transformers, heat recovery steam generator, pumps, and compressors,
etc. have been placed. Purchase orders for almost all of the balance of
mechanical and electrical equipment and materials have also been placed.
Fabrication of all major equipment is well underway and some has been shipped.
In May
2011, a building permit was issued for the project by the City of Mississauga,
and construction began with excavation of the site followed by installation of
the concrete foundations for the buildings and equipment. The foundations for
all power plant buildings are nearing completion, as is the steam turbogenerator
pedestal, the gas turbogenerator pedestal and several other concrete structures.
To view progress photos of the project click on this
link.
|